Building in Martinique and the French Caribbean: earthquake- and hurricane-resistant standards
Martinique is exposed to two major risks for buildings: earthquakes and hurricanes. Seismic standards in Martinique have governed construction for years; since 2025, hurricane-resistant construction in the French Caribbean has had its own regulations. Here is what these rules require of a villa in practice, from the building permit to maintenance.
Architect’s view
Contents
Key takeaways
All of Martinique is in seismic zone 5, the highest level on French territory.
A house is designed either to Eurocode 8 or to the CPMI-EC8 zone 5 guide (2020 edition), the successor to the CP-MI Antilles.
Since January 1, 2024, a seismic compliance certificate (attestation parasismique) has been required with the permit application and again on completion, even for a house.
Since January 1, 2026, houses must comply with the hurricane-resistant building rules: a reference wind speed of 35 m/s in Martinique.
Structural-damage insurance (dommages-ouvrage) is taken out before construction starts.
Seismic standards in Martinique: zone 5 and Eurocode 8
The French Caribbean lies on a subduction zone: the Atlantic ocean floor, carried by the American plates, is sinking beneath the Caribbean plate at a rate of about 2 cm per year. The earthquake of January 11, 1839, killed more than 300 people in Martinique. Since May 1, 2011, the whole island has been classified as seismic zone 5, rated “high”: this is the highest level on French territory, as in Guadeloupe.
A villa falls under importance category II, the category for single-family housing. For zone 5, the Order of October 22, 2010, sets a reference acceleration of 3 m/s². The objective for a house is to avoid collapse: it may be damaged by the reference earthquake, but it must protect its occupants.
Two methods: calculation or the simplified guide
The general rule is Eurocode 8 (NF EN 1998 standards), which requires engineering calculations. For houses that meet its conditions on site, volume, shape and bracing, the CPMI-EC8 zone 5 guide, 2020 edition, provides prescriptive rules. It replaced the former 2004 “CP-MI Antilles” document for permit applications filed since January 1, 2021. Outside its scope, Eurocode 8 is mandatory.
Certificates at the permit stage and on completion
Since January 1, 2024, under Articles R. 122-36 and R. 122-37 of the French Construction and Housing Code (Code de la construction et de l’habitation), the project owner (maître d’ouvrage) of a house located in zone 3, 4 or 5 must have two certificates drawn up:
on filing the building permit application, a certificate of compliance with the seismic rules at the design stage, attached to the application under Article R. 431-16 of the French Urban Planning Code (Code de l’urbanisme);
on completion of the work, a certificate of compliance with these rules, attached to the declaration certifying completion and compliance of the work (Article R. 462-4 of the same Code).
For a house, they may be issued by a technical inspector (contrôleur technique) or by a builder within the meaning of Article 1792-1 of the French Civil Code; their content is set by an order of December 22, 2023. Technical inspection is mandatory only in specific cases, for example in zone 5 when the floor of the top story is more than 8 m above the ground (Article R. 125-17 of the Construction Code). DEAL Martinique (the French State’s environment, planning and housing directorate) may also check compliance with the seismic rules during construction.
Architect’s view
Hurricane-resistant construction in the French Caribbean: the rules in force
The North Atlantic hurricane season officially runs from June 1 to November 30; in the French Caribbean, the risk peaks in August and September. A decree of November 23, 2023, and an order of July 5, 2024 gave Guadeloupe and Martinique mandatory hurricane-resistant building rules. They have applied since January 1, 2025, and since January 1, 2026 for single-family homes and for the windows and doors of all buildings.
The Order classifies buildings into four categories and sets for each a reference wind speed, expressed as a 10-minute average, at a height of 10 m, over flat, open terrain. A villa is in category II.
Category
Examples
Return period
Reference wind speed in Martinique
I
Outbuildings, buildings not classified elsewhere
25 years
30 m/s (108 km/h)
II
Single-family homes and similar buildings
50 years
35 m/s (126 km/h)
III
Schools, certain buildings open to the public, buildings over 28 m tall
50 years
35 m/s (126 km/h)
IV
Civil protection, acute care, essential water and energy networks
100 years
39 m/s (140 km/h)
This speed is adjusted to the site by an exposure coefficient (terrain relief, roughness, height), mapped for Martinique on Géorisques on a 250 m grid: a seafront or clifftop site is more exposed than a sheltered valley. For a house, following the Antilles guide to cyclone-resistant design and construction of single-family homes creates a presumption of compliance, within the limits of its scope: houses of ordinary size and simple shape. Otherwise, the villa must be designed by calculation, according to Eurocode 1 (NF EN 1991-1-4).
Earthquake and hurricane rules are cumulative: a villa must satisfy both sets of regulations, as one does not exempt it from the other.
Architect’s viewArchitect’s view
What these rules change in practice for a villa
Both risks call for the same approach: loads must follow an unbroken path, from the roof down to the foundations.
Foundations, ties and bracing
Soil study: carried out by a geotechnical engineer, it is the first precaution cited by DEAL Martinique.
Foundations: footings embedded at least 30 cm into firm soil, with specific provisions on sloping ground.
Ties, horizontal and vertical, connected to one another; the vertical ties remain straight, with a constant cross-section.
Bracing: walls that run continuously down to the foundations; for seismic-rated hollow bricks, the DEAL expects a thickness of 20 cm and prohibits 15 cm bricks.
Concrete cover over the reinforcement, generally 3.5 to 4.5 cm: it protects the steel from corrosion.
Roof, windows, doors and protection
Roof: four slopes rather than one or two and a pitch close to 30° reduce wind loads.
Overhangs and canopies: they catch the wind. The ministry’s guidance sheets limit the overhang of a roofing sheet beyond the lowest purlin to 10 cm, unless the roof framing is reinforced. A canopy whose failure would threaten the roof is treated as part of the roof.
Fasteners: A4 stainless steel is recommended on the seafront; the connections of elements that could be torn off, such as roofing or siding, are designed with an overstrength factor of 1.5.
Windows and doors: a label must prove they have passed wind tests for the site (from 1,500 to 2,650 Pa in Martinique for a house under 9 m tall, according to the ministry’s guidance sheets) and impact tests; without impact testing, protection is required. Laminated glass is more resistant to impacts.
Shutters: the preferred protection against windborne debris; under the conditions set by the guide, the regulations allow reduced loads for a window protected by a shutter, even a removable one.
Rooftop equipment: photovoltaic panels and solar water heaters are fastened to resist being torn off.
These constraints are compatible with open, ventilated architecture: our guide to the contemporary bioclimatic villa shows how.
Architect’s view
Landslides, marine flooding, PPRN: reading the land before you buy
In Martinique, each municipality has a multi-hazard natural risk prevention plan (PPRN), approved in 2004 and revised in 2013. As a public-interest easement, it is binding on every construction project. A new revision, launched by prefectoral orders of September 3, 2024, covers in particular inland flooding, marine flooding and hurricane swell, ground movements, liquefaction, volcanic hazards and tsunamis.
Depending on the zone in the plan, new construction is prohibited, subject to a prior study, or allowed with requirements. If the PPRN requires a prior study, the permit application must include a certificate from the architect or an expert confirming that it has been carried out (Article R. 431-16 of the French Urban Planning Code). When a property is sold, the seller provides a risk disclosure statement (état des risques, Article L. 125-5 of the French Environmental Code), which you can also generate by address on Géorisques.
The ministry’s guidance sheets consider a building to be on the seafront as soon as it is exposed to sea spray, generally up to 800 m from the shore. Aluminum and stainless steel are better suited there. Contact between incompatible metals, for example aluminum or galvanized steel with copper, must be avoided.
Every year, before hurricane season: inspection of fasteners, roofing sheets, windows and doors, shutters and water drains.
Rinsing of the parts that rain does not wash, with clean water or a pH-neutral product; no chlorinated products or solvents.
Every three years: full inspection of the roof, including edges, laps and fittings.
Any sign of rust is treated without delay; a corroded fastener is replaced.
Visible corrosion on the underside of the roofing sheets may indicate condensation: the roof space then needs better ventilation. This monitoring can be entrusted to an on-site maintenance service, which is useful when you live abroad.
Architect’s viewArchitect’s view
Ten-year liability, structural-damage insurance and hurricanes: who covers what
Three statutory warranties run from the formal acceptance of the work (réception): the completion warranty (garantie de parfait achèvement; 1 year, Article 1792-6 of the French Civil Code), the proper functioning warranty on separable equipment (garantie de bon fonctionnement; at least 2 years, Article 1792-3) and the ten-year builder’s liability (responsabilité décennale; 10 years, Articles 1792 and 1792-4-1). The latter covers damage that compromises the structural soundness of the building or renders it unfit for its intended purpose. Each builder must provide proof of insurance when work starts on site (Article L. 241-1 of the French Insurance Code).
The project owner, for their part, takes out structural-damage insurance before work starts on site (Article L. 242-1). It pays for repairs falling under the ten-year liability without waiting for liability to be established: the insurer gives its decision within 60 days and, if it accepts the claim, makes an offer within 90 days, two deadlines that both run from the date the claim is filed. Failure to take out this insurance is a criminal offense, except for an individual who builds a home to live in themselves or to house their spouse, ascendants or descendants (Article L. 243-3).
Property insurance policies cover wind damage from storms, hurricanes and cyclones. When hurricane winds reach 145 km/h averaged over ten minutes, or 215 km/h in gusts, the natural disaster compensation scheme (régime des catastrophes naturelles) takes over, following an order recognizing the disaster (Articles L. 122-7 and L. 125-1 of the French Insurance Code). Have your policies reviewed by your insurer or a broker.
VillaDesign Caraïbes assists with land selection and the feasibility study, then designs and builds the turnkey villa, with a single point of contact and dated construction photos published as work progresses. To discuss your project, contact us.
This guide provides general guidance, checked as of the update date. It does not replace the advice of a notary, a lawyer or a tax advisor on your situation.
FAQ
Frequently asked questions
Short answers to the questions we are asked most often on this topic.
Is all of Martinique in seismic zone 5?
Yes. The regulatory seismic zoning, which came into force on May 1, 2011, places the whole of Martinique in zone 5, defined as high seismicity, like Guadeloupe. This is the highest level on French territory. A new house must therefore comply with the seismic rules.
Is the CP-MI Antilles guide still valid?
No, not for a new project. For permit applications filed since January 1, 2021, it has been replaced by the CPMI-EC8 zone 5 guide, 2020 edition, which sets simplified rules for houses that meet its conditions. Outside its scope, design follows Eurocode 8.
Who signs the seismic compliance certificate for a single-family home?
Since January 1, 2024, it may be issued by a technical inspector (contrôleur technique) or by a builder within the meaning of Article 1792-1 of the French Civil Code. A first certificate is attached to the building permit application, and a second to the declaration of completion of the work. Their content is set by the Order of December 22, 2023.
Do the hurricane-resistant building rules apply to my future villa?
Yes, if it is new and requires a building permit or a prior declaration (déclaration préalable). For single-family homes, the Order of July 5, 2024, has applied since January 1, 2026. It also covers certain major work on an existing building, such as an extension of more than 20% of the original surface area.
What does insurance cover in the event of a hurricane?
Property insurance policies cover damage caused by wind from storms, hurricanes and cyclones. At or above a mean wind speed of 145 km/h over ten minutes, or 215 km/h in gusts, the natural disaster compensation scheme (régime des catastrophes naturelles) takes over, following an interministerial order recognizing the disaster. Have your insurer check deductibles and exclusions.
Do you need a technical inspection firm (bureau de contrôle) to build a villa?
For a house, technical inspection (contrôle technique) is mandatory only in specific cases, for example in zone 5 when the floor of the top story is more than 8 m above the ground. It remains possible on a voluntary basis. If in doubt, DEAL Martinique (the French State’s environment, planning and housing directorate) recommends engaging a technical inspection firm to monitor the work.